Olds residents are voicing their concerns and frustrations over a massive proposed data centre campus in the southern Alberta ...
An application to build a 1.4GW gas-fired power plant for a data center campus in the central Alberta city of Olds has been rejected by the Canadian province’s utilities commission.
The development permit application tied to the proposed Synapse data centre project in Olds has been withdrawn, according to information published on the Town of Olds website. Project information ...
The Alberta Utilities Commission has closed an application to build a 1,400-megawatt natural gas-fired power plant in Olds tied to the proposed Synapse data centre project. In a March 6 letter, the ...
8don MSN
Alberta Utilities Commission nixes power plant proposal for Canada’s largest AI data centre complex
The Alberta Utilities Commission (AUC) has rejected Synapse Real Estate Corp.’s application to construct a 1.4-gigawatt natural gas-fired power plant in the town of Olds, Alta., saying the application ...
OLDS — The Alberta Utilities Commission (AUC) has closed an application by Synapse Real Estate to build and operate a 1,400-megawatt (MW) natural gas-fired power plant in northeast Olds as part of a ...